Tag Archives: USS Ross (DDG 71)

Burke Repair! Get Your (Overseas) Burke Repair!

NORFOLK, Va. (May 16, 2026) – Arleigh Burke-class guided-missile destroyer USS Mahan (DDG 72) returns to Naval Station Norfolk, May 16, 2026, following a historic 11-month deployment to U.S. 2nd, 4th, 5th, and 6th Fleets as part of the Gerald R. Ford Carrier Strike Group. During their historic deployment across four fleets, the crew of Mahan conducted 19 replenishments-at-sea and executed 25 sea and anchor details. (U.S. Navy photo by Chief Mass Communication Specialist David Smalls, III)

The U.S. Navy has 75 active Arleigh Burke-class guided-missile destroyers, 10 under construction, and 13 more on order, for a planned total of 99. Without a doubt, they are the backbone of the Fleet, which only has about 115 active surface combatants of all types (DDG, LCS, CG).

However, on the current 36-month OFRP block, each of these active ships needs to undergo a 6-8 month Selected Restricted Availability (SRA/DSRA), including a dry-docking every five years or so, and shorter 2-4 weeks-long Continuous Maintenance Availabilities (CMAV).

┌──────────────────────────────────────────────────────────┐
│ 36-Month OFRP Cycle Rotation │
└──────────────────────────────────────────────────────────┘
│
├── 1. Maintenance Phase (Approx. 6–7 Months)
│ • Selected Restricted Availability (SRA)
│ • Drydocking Selected Restricted Availability (DSRA)
│
├── 2. Basic Training Phase (Approx. 4–5 Months)
│ • Systems integration, unit-level certifications
│
├── 3. Integrated Phase (Approx. 2–3 Months)
│ • Strike Group integration exercises (COMPTUEX)
│
├── 4. Deployment Phase (7–8 Months standard)
│ • Overseas combatant command deployment
│
└── 5. Sustainment Phase (Remaining months)
• High-readiness surge state; routine pierside repairs (CMAVs)

Then, with old ships at mid-life, an 18-24 month DDG MOD 2.0 Modernization is on the table, followed by at least a final SLEP at the 30-year mark. Keep in mind that Burke herself is 35 years old and still going strong. 

It looks something like this when you put it together:

Timeline / Ship Age Maintenance Milestone Primary Focus & Scope
Years 5–10 First Major DSRA Structural hull inspection, tank preservation, shaft pulling, sonar dome maintenance, and Baseline Aegis software/hardware upgrades.
Years 15–20 Mid-Life Mid-Period Availability (MPA) Major machinery overhaul, generator refurbishments, habitability upgrades, and combat system patch updates.
Years 20–25 DDG MOD 2.0 / Modernization Overhaul Comprehensive mid-life modernization lasting 18 to 24 months. Includes structural retrofits, installing modern combat systems (e.g., Aegis Baseline 9/10), SEWIP Block III electronic warfare suites, upgraded SPY radar arrays, and major hull/mechanical refreshes.
Years 30–35+ Service Life Extension Program (SLEP) Deep structural hull/piping repairs, main reduction gear re-alignments, and system overhauls to extend operational readiness beyond the original 35-year design life out to 40+ years.

Now multiply that by 75 hulls (soon to be 99), and you get the idea of why the Navy has maintenance backlogs.

While only two shipyards make Burkes (Ingalls at Pascagoula and Bath in Maine), just three East Coast yards (BAE Systems Norfolk, General Dynamics NNS, and BAE Systems Jacksonville), and four West Coast yards (General Dynamics NASSCO, BAE Systems San Diego, Continental Maritime of San Diego, and Vigor in Seattle) do almost all the maintenance work.

The Navy’s four public yards prioritize nuclear ships (CVNs, SSBNs, SSGNs, and SSNs) and have no bandwidth for DDGs.

Forward-deployed tin cans get a shorter refresh at Navantia (five Rota-based FDNF Europe destroyers in 6th Fleet) and via SRF-JRMC (10 7th Fleet DDGs of DESRON 15 at Japanese yards such as Sumitomo and Mitsubishi). Don’t be surprised to see 7th Fleet tin cans in South Korean yards at some point in the near future as well.

With that being said, there are changes afoot to help alleviate the maintenance burden on CONUS yards.

Navantia recently started including drydocking in its maintenance schedule, the first since the 2014 arrival of FDNF-E destroyers.

Arleigh Burke-class guided-missile destroyer USS Arleigh Burke (DDG 51) sits in dry dock at Navantia Shipyard in Cadiz Oct. 8, 2026. The evolution marks the first dry docking of a U.S. Navy warship in the U.S. 6th Fleet area of operations since the arrival of Forward Deployed Naval Forces-Europe destroyers and expands forward-deployed maintenance capability and readiness generation. (U.S. Navy photo by Mass Communication Specialist 2nd Class Jett Morgan)

Likewise, the Forward Deployed Regional Maintenance Center (FDRMC) recently completed a week-long pier-side voyage repair period in Mombasa, Kenya, aboard the destroyer USS Ross (DDG 71), marking the first U.S. Navy ship maintenance availability in Mombasa in recent years. Ross is part of the George H.W. Bush Carrier Strike Group and had been deployed for six months when it swung by Mombasa.

A rough Ross arriving in Mombasa, 5 September 2026. 260905-N-NO901-1002

A more trim Ross leaving Mombasa, 10 September 2026. 260910-O-N0901-1001

With 350 military and civilian personnel based out of Naples, FDRMC is a globe-trotting group able to roam around 5th and 6th Fleet areas and use friendly ports for short repairs. Such groups will be invaluable in any Pacific war (or continued Middle East war with Bahrain vorboten), and more should be stood up. Pronto.

Speaking of which, Austal USA launched AFDM 15 this summer, the U.S. Navy’s first Auxiliary Floating Dry Dock Medium built in more than 40 years. The dock can service DDGs, CGs, LCSs, & LSDs, etc.

The Navy had 14 such AFDMs during the Cold War, but now AFDM-15 is the only one, with no more on order.

As Salamander says, that is a crime, and at least four should be bought, as a minimum.

Last of the Rota 4 heads across the pond

The Big Blue first announced in 2012 they were sending a quartet of ABM-enabled Burkes to Spain where they would be forward deployed for emerging threats and provide NATO with some solid ballistic missile defense. Since then, three have gone over and even gotten involved in the Black Sea to a degree in the new cool war between the West and a resurgent Russia.

Now it looks like they will soon be full-up.

10016-N-7408S-012 MEDITTERANNEAN SEA (Jan. 16, 2010) Waves crash over the bow of the guided-missile destroyer USS Carney (DDG 64). Carney is part of the Eisenhower Carrier Strike Group and is deployed as part of an on-going rotation of forward-deployed forces to support maritime security operations in the U.S. 5th and 6th Fleet areas of responsibility. (U.S. Navy photo by Master at Arms Chief Chief Anthony J. Sganga/Released)

10016-N-7408S-012 MEDITTERANNEAN SEA (Jan. 16, 2010) Waves crash over the bow of the guided-missile destroyer USS Carney (DDG 64). Carney is part of the Eisenhower Carrier Strike Group and is deployed as part of an on-going rotation of forward-deployed forces to support maritime security operations in the U.S. 5th and 6th Fleet areas of responsibility. (U.S. Navy photo by Master at Arms Chief Chief Anthony J. Sganga/Released)

Per USN:

USS Carney (DDG 64) departed her homeport of Mayport, Florida, Sept. 6 on her way to Rota, Spain, as the final of four Arleigh Burke-class guided-missile destroyers to be forward deployed to Spain.

To enhance the security of the European region, Carney will join USS Donald Cook (DDG 75), USS Ross (DDG 71), and USS Porter (DDG 78) who have already made the transition to Spain.

“USS Carney and her crew will play a crucial role in the U.S. contribution to NATO’s ballistic missile defense efforts,” said Vice Adm. James Foggo III, commander, U.S. 6th Fleet. “Our forward deployed naval forces (FDNF) based in Rota provide a credible capability and support NATO’s broader commitment to regional security.”

US Navy DDGs arrive in Spain to begin ABM Watch over Europe

Standard Missile-3 (SM-3) launches from the guided-missile destroyer USS Fitzgerald (DDG 62) as apart of a joint ballistic missile defense exercise. The new ABM capable DDGs carrying the SM-3 will provide a limited missile umbrella over Europe and North Africa

Standard Missile-3 (SM-3) launches from the guided-missile destroyer USS Fitzgerald (DDG 62) as apart of a joint ballistic missile defense exercise. The new ABM capable DDGs carrying the SM-3 will provide a limited missile umbrella over Europe and North Africa. Click to embiggen

NNS140211-05. USS Donald Cook Begins Forward Deployment to Rota, Spain,

From Commander, U.S. Naval Forces Europe-Africa/U.S. 6th Fleet Public Affairs

ROTA, Spain (NNS) — The Arleigh Burke-class guided-missile destroyer USS Donald Cook (DDG 75) arrived at Naval Station Rota to begin her forward deployment to the U.S. 6th Fleet area of operations, Feb. 11.

Donald Cook is the first of four Arleigh Burke-class guided-missile destroyers to be stationed in the U.S. 6th Fleet area of operations, and will be joined by other guided-missile destroyers, USS Ross (DDG 71), USS Porter (DDG 78) and USS Carney (DDG 64), over the next two years.

The purpose behind these destroyers’ forward deployments is to enhance the security of the European region. While in U.S. 6th Fleet, these ships will perform numerous missions, including NATO ballistic missile defense, maritime security operations, bi-lateral and multi-lateral training exercises, and NATO operations and deployments.

Ross is scheduled to join Donald Cook in Rota later this year, with Carney and Porter arriving sometime in 2015.